Customers are requested to make base concrete according to the designed specifications and the strength of the site.
Anchor bolts are to be fixed by our agents.
The required strength of the base concrete must be at least 180Kg/cm2.
The thickness of mortar on the base concrete must not exceed 20mm.
If the customer designates the size of sockets for plumbing, our agents will install the sockets.
After the sockets are in place, the plumbing and heat insulation must be done by customer.
Do not place heavy loads or force on the panels during the transportation. Those parts that are touched with rope or other cargo must be cushioned.
Be careful not to put any heavy weight on the pipes that are connected to the fitting.
Pipe installation must be started from the water tank side and be careful not to put unbalanced weight on the fitting.
Take precautions to avoid fire or other occurrences / accidents while welding.
If it is not used for a long time, be sure to drain the water from the tank.
As the tank is a reservoir of water for consumption by people, regular inspection should be done for safety (more than twice a year)
American Composite Technology LLC
4500 9th Avenue NE, Suite 300,
Seattle, WA 98105,USA
Tel : +1(206) 900-9194
1271-4, Samgye-dong,
Gimhae-si, Gyungnam,
South Korea.
Advanced Fiberglass Industry LLC
United Arab Emirates
Tel : +97167672611
Email : sales@advancedfiberglassllc.com
Continas Industries
Signet Hub, Akshar Chowk
OP Road, Vadodara, Gujarat
Email : info@continas.com